| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Big Time Multimedia Producers | 125 days | Mon 02/06/03 | Fri 21/11/03 | | 0% |
| 2 | Vision / Scope | 5 days | Mon 02/06/03 | Fri 06/06/03 | Management[10%],Project Manager[10%],Instructional Designer[10%],Sales Manager[10%],Marketing Manager[10%],Distribution Manager[10%] | 0% |
| 3 | Determine project scope (goals, concept, time, staffing, budget, promotion, etc…) | 2 days | Mon 02/06/03 | Tue 03/06/03 | | 0% |
| 4 | Define preliminary resource | 1 day | Wed 04/06/03 | Wed 04/06/03 | | 0% |
| 5 | Secure core resources | 1 day | Thu 05/06/03 | Thu 05/06/03 | | 0% |
| 6 | Determine major milestones | 1 day | Fri 06/06/03 | Fri 06/06/03 | | 0% |
| 7 | Vision / Scope complete | 0 days | Fri 06/06/03 | Fri 06/06/03 | | 0% |
| 8 | Analysis | 13.5 days | Mon 09/06/03 | Thu 26/06/03 | Management[10%],Project Manager[10%],Instructional Designer[10%],Sales Manager[10%],Marketing Manager[10%],Distribution Manager[10%] | 0% |
| 9 | Conduct needs analysis | 5 days | Mon 09/06/03 | Fri 13/06/03 | | 0% |
| 10 | Develop preliminary budget | 2 days | Mon 16/06/03 | Tue 17/06/03 | | 0% |
| 11 | Discuss project scope and budget with team | 2 days | Wed 18/06/03 | Thu 19/06/03 | | 0% |
| 12 | Incorporated feedback | 4 hrs | Fri 20/06/03 | Fri 20/06/03 | | 0% |
| 13 | Develop delivery schedule | 1 day | Mon 23/06/03 | Mon 23/06/03 | | 0% |
| 14 | Obtain approval to proceed | 4 hrs | Tue 24/06/03 | Tue 24/06/03 | | 0% |
| 15 | Secure required resources | 4 hrs | Tue 24/06/03 | Tue 24/06/03 | | 0% |
| 16 | Analysis complete | 0 days | Tue 24/06/03 | Tue 24/06/03 | | 0% |
| 17 | Instructional Design | 11.5 days | Wed 11/06/03 | Thu 26/06/03 | Management[10%],Project Manager[10%],Instructional Designer[80%] | 0% |
| 18 | Decide on colour / theme | 4 hrs | Wed 11/06/03 | Wed 11/06/03 | | 0% |
| 19 | Decide on content (compact, chunking, simplicity, objectives in each year, summaries of each year) | 5 days | Thu 12/06/03 | Wed 18/06/03 | | 0% |
| 20 | Decide on photos | 5 days | Thu 12/06/03 | Wed 18/06/03 | | 0% |
| 21 | Decide on audio | 5 days | Thu 12/06/03 | Wed 18/06/03 | | 0% |
| 22 | Decide on video | 5 days | Thu 12/06/03 | Wed 18/06/03 | | 0% |
| 23 | Decide on FAQ | 5 days | Thu 19/06/03 | Wed 25/06/03 | | 0% |
| 24 | Obtain approval to proceed | 4 hrs | Thu 26/06/03 | Thu 26/06/03 | | 0% |
| 25 | Instructional design complete | 0 days | Thu 26/06/03 | Thu 26/06/03 | | 0% |
| 26 | Development | 105 days | Mon 02/06/03 | Fri 24/10/03 | Management[10%],Project Manager[25%],Instructional Designer[20%],Testers | 0% |
| 27 | Interface design | 72 days | Thu 26/06/03 | Mon 06/10/03 | | 0% |
| 28 | Decide on colour/ theme | 4 hrs | Thu 26/06/03 | Thu 26/06/03 | | 0% |
| 29 | Decide on images | 2 days | Thu 26/06/03 | Fri 27/06/03 | | 0% |
| 30 | Decide on links | 3 days | Mon 30/06/03 | Wed 02/07/03 | | 0% |
| 31 | Create template | 5 days | Thu 03/07/03 | Wed 09/07/03 | | 0% |
| 32 | Obtain approval to proceed | 4 hrs | Thu 10/07/03 | Thu 10/07/03 | | 0% |
| 33 | Interface design complete | 0 days | Mon 06/10/03 | Mon 06/10/03 | | 0% |
| 34 | Content | 105 days | Mon 02/06/03 | Fri 24/10/03 | | 0% |
| 35 | Write summaries | 61.5 days | Thu 26/06/03 | Fri 19/09/03 | | 0% |
| 36 | Decide on font style | 2 hrs | Thu 26/06/03 | Thu 26/06/03 | | 0% |
| 37 | Decide on length | 2 hrs | Thu 26/06/03 | Thu 26/06/03 | | 0% |
| 38 | Obtain approval to proceed | 4 hrs | Fri 19/09/03 | Fri 19/09/03 | | 0% |
| 39 | Summaries complete | 0 days | Fri 19/09/03 | Fri 19/09/03 | | 0% |
| 40 | Decide on photos | 12.5 days | Thu 26/06/03 | Mon 14/07/03 | | 0% |
| 41 | Shoot photos | 5 days | Thu 26/06/03 | Wed 02/07/03 | | 0% |
| 42 | Find reseller | 7 days | Thu 26/06/03 | Fri 04/07/03 | | 0% |
| 43 | Obtain approval to proceed | 4 hrs | Mon 14/07/03 | Mon 14/07/03 | | 0% |
| 44 | Photos selected | 0 days | Mon 14/07/03 | Mon 14/07/03 | | 0% |
| 45 | Create audio | 62 days | Thu 26/06/03 | Fri 19/09/03 | | 0% |
| 46 | Record | 57 days | Thu 26/06/03 | Fri 12/09/03 | | 0% |
| 47 | Edit | 57 days | Thu 26/06/03 | Fri 12/09/03 | | 0% |
| 48 | Digitize | 5 days | Mon 15/09/03 | Fri 19/09/03 | | 0% |
| 49 | Obtain approval to proceed | 4 hrs | Fri 19/09/03 | Fri 19/09/03 | | 0% |
| 50 | Audio complete | 0 days | Fri 19/09/03 | Fri 19/09/03 | | 0% |
| 51 | Create Video | 62 days | Thu 26/06/03 | Fri 19/09/03 | | 0% |
| 52 | Shoot | 42 days | Thu 26/06/03 | Fri 22/08/03 | | 0% |
| 53 | Edit | 52 days | Thu 26/06/03 | Fri 05/09/03 | | 0% |
| 54 | Digitize | 62 days | Thu 26/06/03 | Fri 19/09/03 | | 0% |
| 55 | Obtain approval to proceed | 4 hrs | Fri 19/09/03 | Fri 19/09/03 | | 0% |
| 56 | Video complete | 0 days | Fri 19/09/03 | Fri 19/09/03 | | 0% |
| 57 | Create FAQ (help section) | 16 days | Mon 22/09/03 | Mon 13/10/03 | | 0% |
| 58 | Decide on font style | 2 hrs | Mon 22/09/03 | Mon 22/09/03 | | 0% |
| 59 | Decide on length | 2 hrs | Mon 22/09/03 | Mon 22/09/03 | | 0% |
| 60 | Obtain approval to proceed | 4 hrs | Mon 13/10/03 | Mon 13/10/03 | | 0% |
| 61 | FAQ complete | 0 days | Mon 13/10/03 | Mon 13/10/03 | | 0% |
| 62 | Evaluation | 105 days | Mon 02/06/03 | Fri 24/10/03 | | 0% |
| 63 | Select testers | 2 days | Mon 02/06/03 | Tue 03/06/03 | | 0% |
| 64 | Alpha Testing | 5 days | Mon 06/10/03 | Fri 10/10/03 | | 0% |
| 65 | Beta Testing | 5 days | Mon 20/10/03 | Fri 24/10/03 | | 0% |
| 66 | Evaluation complete | 0 days | Fri 24/10/03 | Fri 24/10/03 | | 0% |
| 67 | Approval | 2 days | Thu 30/10/03 | Mon 03/11/03 | Management[40%],Project Manager[25%],Sales Manager[10%],Marketing Manager[10%] | 0% |
| 68 | Obtain approval to proceed | 2 days | Thu 30/10/03 | Fri 31/10/03 | | 0% |
| 69 | Approval complete | 0 days | Mon 03/11/03 | Mon 03/11/03 | | 0% |
| 70 | Sales and Marketing and Distribution | 54 days | Tue 02/09/03 | Fri 14/11/03 | Management[30%],Project Manager[15%],Sales Manager[75%],Marketing Manager[75%],Distribution Manager[75%] | 0% |
| 71 | Marketing | 54 days | Tue 02/09/03 | Fri 14/11/03 | | 0% |
| 72 | Create cover design | 21 days | Fri 19/09/03 | Fri 17/10/03 | | 0% |
| 73 | Decide on colour / theme | 1 day | Fri 19/09/03 | Fri 19/09/03 | | 0% |
| 74 | Decide on packaging | 5 days | Fri 19/09/03 | Thu 25/09/03 | | 0% |
| 75 | Obtain approval to proceed | 4 hrs | Fri 17/10/03 | Fri 17/10/03 | | 0% |
| 76 | Cover design complete | 0 days | Fri 17/10/03 | Fri 17/10/03 | | 0% |
| 77 | Advertisement | 54 days | Tue 02/09/03 | Fri 14/11/03 | | 0% |
| 78 | Decide on demographics | 54 days | Tue 02/09/03 | Fri 14/11/03 | | 0% |
| 79 | Select radio ads | 54 days | Tue 02/09/03 | Fri 14/11/03 | | 0% |
| 80 | Select TV ads | 54 days | Tue 02/09/03 | Fri 14/11/03 | | 0% |
| 81 | Select print ads | 54 days | Tue 02/09/03 | Fri 14/11/03 | | 0% |
| 82 | Select web ads | 54 days | Tue 02/09/03 | Fri 14/11/03 | | 0% |
| 83 | Obtain approval to proceed | 4 hrs | Fri 14/11/03 | Fri 14/11/03 | | 0% |
| 84 | Advertisement complete | 0 days | Fri 14/11/03 | Fri 14/11/03 | | 0% |
| 85 | Sales | 5 days | Mon 10/11/03 | Fri 14/11/03 | | 0% |
| 86 | Train sales force | 5 days | Mon 10/11/03 | Fri 14/11/03 | | 0% |
| 87 | Sales training complete | 0 days | Fri 14/11/03 | Fri 14/11/03 | | 0% |
| 88 | Distribution | 2 days | Mon 10/11/03 | Tue 11/11/03 | | 0% |
| 89 | Train distribution division | 2 days | Mon 10/11/03 | Tue 11/11/03 | | 0% |
| 90 | Distribution training complete | 0 days | Mon 10/11/03 | Mon 10/11/03 | | 0% |
| 91 | Project Evaluation | 10 days | Mon 10/11/03 | Fri 21/11/03 | Management[5%],Project Manager[5%],Sales Manager[5%],Marketing Manager[5%],Distribution Manager[5%],Instructional Designer[5%] | 0% |
| 92 | Performance Evaluation | 5 days | Mon 10/11/03 | Fri 14/11/03 | | 0% |
| 93 | Performance against goals | 5 days | Mon 10/11/03 | Fri 14/11/03 | | 0% |
| 94 | Performance against schedule | 5 days | Mon 10/11/03 | Fri 14/11/03 | | 0% |
| 95 | Performance against quality | 5 days | Mon 10/11/03 | Fri 14/11/03 | | 0% |
| 96 | Performance against budget | 5 days | Mon 10/11/03 | Fri 14/11/03 | | 0% |
| 97 | Performance evaluation complete | 0 days | Fri 14/11/03 | Fri 14/11/03 | | 0% |
| 98 | Project Planning Evaluation | 5 days | Mon 17/11/03 | Fri 21/11/03 | | 0% |
| 99 | Identify limitations (well defined plan, meetings, communication, changes, etc…) | 5 days | Mon 17/11/03 | Fri 21/11/03 | | 0% |
| 100 | Make recommendations | 5 days | Mon 17/11/03 | Fri 21/11/03 | | 0% |
| 101 | Project evaluation complete | 0 days | Fri 21/11/03 | Fri 21/11/03 | | 0% |