| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | KPM Group | 49 days | Thu 03/07/03 | Tue 09/09/03 | Management,Project Manager,Instructor[50%],Instructional Designer,Developer 1,Developer 2,Support Staff[75%],Graphics Support[50%] | 0% |
| 2 | Vision / Scope | 3 days | Thu 03/07/03 | Tue 08/07/03 | | 0% |
| 3 | Determine project scope (goals, concept, time, staffing, budget, promotion, etc…) | 1 day | Thu 03/07/03 | Thu 03/07/03 | Project Manager[5%] | 0% |
| 4 | Define preliminary resource | 4 hrs | Fri 04/07/03 | Fri 04/07/03 | Project Manager[5%] | 0% |
| 5 | Secure core resources | 4 hrs | Fri 04/07/03 | Fri 04/07/03 | Project Manager[5%] | 0% |
| 6 | Determine major milestones | 1 day | Mon 07/07/03 | Mon 07/07/03 | Project Manager[5%] | 0% |
| 7 | Vision / Scope complete | 0 days | Tue 08/07/03 | Tue 08/07/03 | | 0% |
| 8 | Analysis | 4 days | Wed 09/07/03 | Tue 15/07/03 | | 0% |
| 9 | Develop preliminary budget | 4 hrs | Wed 09/07/03 | Wed 09/07/03 | Project Manager[5%] | 0% |
| 10 | Discuss project scope and budget with management | 4 hrs | Wed 09/07/03 | Wed 09/07/03 | Project Manager[5%] | 0% |
| 11 | Incorporated feedback | 4 hrs | Thu 10/07/03 | Thu 10/07/03 | Management[5%],Project Manager[5%] | 0% |
| 12 | Develop delivery schedule | 1 day | Fri 11/07/03 | Fri 11/07/03 | Project Manager[10%] | 0% |
| 13 | Obtain approval to proceed | 4 hrs | Mon 14/07/03 | Mon 14/07/03 | Management[5%],Project Manager[5%] | 0% |
| 14 | Secure required resources | 4 hrs | Mon 14/07/03 | Mon 14/07/03 | Project Manager[5%] | 0% |
| 15 | Analysis complete | 0 days | Tue 15/07/03 | Tue 15/07/03 | | 0% |
| 16 | Instructional Design | 1.25 days | Wed 16/07/03 | Thu 17/07/03 | | 0% |
| 17 | Decide on content | 4 hrs | Wed 16/07/03 | Wed 16/07/03 | Instructional Designer[50%],Project Manager[5%],Instructor[10%] | 0% |
| 18 | Decide on animation | 2 hrs | Wed 16/07/03 | Wed 16/07/03 | Instructional Designer[50%],Project Manager[2%],Developer 1[2%],Instructor[10%] | 0% |
| 19 | Decide on simulation | 2 hrs | Wed 16/07/03 | Wed 16/07/03 | Instructional Designer[50%],Project Manager[2%],Developer 1[2%],Instructor[10%] | 0% |
| 20 | Decide on practice questions and problems | 2 hrs | Wed 16/07/03 | Wed 16/07/03 | Instructional Designer[50%],Project Manager[2%],Instructor[10%],Developer 2[2%] | 0% |
| 21 | Obtain approval to proceed | 2 hrs | Thu 17/07/03 | Thu 17/07/03 | Project Manager[5%] | 0% |
| 22 | Instructional design complete | 0 days | Thu 17/07/03 | Thu 17/07/03 | | 0% |
| 23 | Development | 41 days | Thu 03/07/03 | Thu 28/08/03 | | 0% |
| 24 | Interface design | 2.25 days | Fri 18/07/03 | Tue 22/07/03 | | 0% |
| 25 | Decide on colour/ theme | 1 hr | Fri 18/07/03 | Fri 18/07/03 | Developer 1[5%],Developer 2[5%],Graphics Support[5%] | 0% |
| 26 | Decide on images | 1 hr | Fri 18/07/03 | Fri 18/07/03 | Developer 1[5%],Developer 2[5%],Graphics Support[5%] | 0% |
| 27 | Decide on links | 1 hr | Fri 18/07/03 | Fri 18/07/03 | Developer 1[5%],Developer 2[5%],Graphics Support[5%] | 0% |
| 28 | Create template | 1 day | Mon 21/07/03 | Mon 21/07/03 | Developer 1[5%],Developer 2[5%],Graphics Support[5%] | 0% |
| 29 | Obtain approval to proceed | 2 hrs | Tue 22/07/03 | Tue 22/07/03 | Project Manager[5%] | 0% |
| 30 | Interface design complete | 0 days | Tue 22/07/03 | Tue 22/07/03 | | 0% |
| 31 | Graphics Development | 19.5 days | Thu 03/07/03 | Wed 30/07/03 | | 0% |
| 32 | Animation | 19.5 days | Thu 03/07/03 | Wed 30/07/03 | | 0% |
| 33 | Module 1: Correlations | 0 days | Thu 03/07/03 | Thu 03/07/03 | | 0% |
| 34 | Target animations | 0 days | Thu 03/07/03 | Thu 03/07/03 | Developer 1[0%] | 0% |
| 35 | Develop animations | 0 days | Thu 03/07/03 | Thu 03/07/03 | Developer 1[0%] | 0% |
| 36 | Module 1: Correlations animation complete | 0 days | Thu 03/07/03 | Thu 03/07/03 | | 0% |
| 37 | Module 2: Regressions | 0 days | Thu 03/07/03 | Thu 03/07/03 | | 0% |
| 38 | Target animations | 0 days | Thu 03/07/03 | Thu 03/07/03 | Developer 1[0%] | 0% |
| 39 | Develop animations | 0 days | Thu 03/07/03 | Thu 03/07/03 | Developer 1[0%] | 0% |
| 40 | Module 2: Regressions animations complete | 0 days | Thu 03/07/03 | Thu 03/07/03 | | 0% |
| 41 | Module 3: Analysis of Variance | 13.5 days | Thu 03/07/03 | Tue 22/07/03 | | 0% |
| 42 | Target animations | 0 days | Thu 03/07/03 | Thu 03/07/03 | Developer 1[0%] | 0% |
| 43 | Develop animations | 4 hrs | Tue 22/07/03 | Tue 22/07/03 | Developer 1[4%],Graphics Support[2%] | 0% |
| 44 | Module 3: Analysis of Variance animations complete | 0 days | Tue 22/07/03 | Tue 22/07/03 | | 0% |
| 45 | Module 4: Non-Parametric Statistics | 3 days | Wed 23/07/03 | Fri 25/07/03 | | 0% |
| 46 | Target animations | 12 hrs | Wed 23/07/03 | Thu 24/07/03 | Developer 1[10%],Graphics Support[5%] | 0% |
| 47 | Develop animations | 12 hrs | Thu 24/07/03 | Fri 25/07/03 | Developer 1[10%],Graphics Support[5%] | 0% |
| 48 | Module 4: Non-Parametric Statistics animations complete | 0 days | Fri 25/07/03 | Fri 25/07/03 | | 0% |
| 49 | Module 5: Lying with Statistics | 2.5 days | Mon 28/07/03 | Wed 30/07/03 | | 0% |
| 50 | Target animations | 12 hrs | Mon 28/07/03 | Tue 29/07/03 | Developer 1[10%],Graphics Support[5%] | 0% |
| 51 | Develop animations | 12 hrs | Tue 29/07/03 | Wed 30/07/03 | Developer 1[10%],Graphics Support[5%] | 0% |
| 52 | Module 5: Lying with Statistics animations complete | 0 days | Wed 30/07/03 | Wed 30/07/03 | | 0% |
| 53 | Simulation | 32 days | Thu 03/07/03 | Fri 15/08/03 | | 0% |
| 54 | Module 1: Correlations | 0 days | Thu 03/07/03 | Thu 03/07/03 | | 0% |
| 55 | Target simulation | 0 days | Thu 03/07/03 | Thu 03/07/03 | Developer 1[0%] | 0% |
| 56 | Develop simulation | 0 days | Thu 03/07/03 | Thu 03/07/03 | Developer 1[0%] | 0% |
| 57 | Module 1: Correlations simulation complete | 0 days | Thu 03/07/03 | Thu 03/07/03 | | 0% |
| 58 | Module 2: Regressions | 2 days | Thu 31/07/03 | Fri 01/08/03 | | 0% |
| 59 | Target simulation | 0 days | Thu 31/07/03 | Thu 31/07/03 | Developer 1[0%] | 0% |
| 60 | Develop simulation | 2 days | Thu 31/07/03 | Fri 01/08/03 | Developer 1[10%],Graphics Support[5%] | 0% |
| 61 | Module 2: Regressions simulation complete | 0 days | Fri 01/08/03 | Fri 01/08/03 | | 0% |
| 62 | Module 3: Analysis of Variance | 24 days | Thu 03/07/03 | Tue 05/08/03 | | 0% |
| 63 | Target simulation | 0 days | Thu 03/07/03 | Thu 03/07/03 | Developer 1[0%] | 0% |
| 64 | Develop simulation | 2 days | Mon 04/08/03 | Tue 05/08/03 | Graphics Support[5%],Developer 1[10%] | 0% |
| 65 | Module 3: Analysis of Variance simulation complete | 0 days | Tue 05/08/03 | Tue 05/08/03 | | 0% |
| 66 | Module 4: Non-Parametric Statistics | 4 days | Wed 06/08/03 | Mon 11/08/03 | | 0% |
| 67 | Target simulation | 2 days | Wed 06/08/03 | Thu 07/08/03 | Developer 1[15%],Graphics Support[3%] | 0% |
| 68 | Develop simulation | 2 days | Fri 08/08/03 | Mon 11/08/03 | Developer 1[15%] | 0% |
| 69 | Module 4: Non-Parametric Statistics simulation complete | 0 days | Mon 11/08/03 | Mon 11/08/03 | | 0% |
| 70 | Module 5: Lying with Statistics | 4 days | Tue 12/08/03 | Fri 15/08/03 | | 0% |
| 71 | Target simulation | 2 days | Tue 12/08/03 | Wed 13/08/03 | Developer 1[15%] | 0% |
| 72 | Develop simulation | 2 days | Thu 14/08/03 | Fri 15/08/03 | Developer 1[15%] | 0% |
| 73 | Module 5: Lying with Statistics simulation complete | 0 days | Fri 15/08/03 | Fri 15/08/03 | | 0% |
| 74 | Content Development | 29 days | Thu 03/07/03 | Tue 12/08/03 | | 0% |
| 75 | Module 1: Correlations | 15 days | Thu 03/07/03 | Wed 23/07/03 | | 0% |
| 76 | Gather content | 0 days | Thu 03/07/03 | Thu 03/07/03 | Instructional Designer[0%],Instructor[0%] | 0% |
| 77 | Develop content | 2 days | Tue 22/07/03 | Wed 23/07/03 | Developer 2[10%] | 0% |
| 78 | Module 1: Correlations content complete | 0 days | Wed 23/07/03 | Wed 23/07/03 | | 0% |
| 79 | Module 2: Regressions | 17 days | Thu 03/07/03 | Fri 25/07/03 | | 0% |
| 80 | Gather content | 0 days | Thu 03/07/03 | Thu 03/07/03 | Instructional Designer[0%],Instructor[0%] | 0% |
| 81 | Develop content | 2 days | Thu 24/07/03 | Fri 25/07/03 | Developer 2[10%] | 0% |
| 82 | Module 2: Regressions content complete | 0 days | Fri 25/07/03 | Fri 25/07/03 | | 0% |
| 83 | Module 3: Analysis of Variance | 19 days | Thu 03/07/03 | Tue 29/07/03 | | 0% |
| 84 | Gather content | 0 days | Thu 03/07/03 | Thu 03/07/03 | Instructional Designer[0%],Instructor[0%] | 0% |
| 85 | Develop content | 2 days | Mon 28/07/03 | Tue 29/07/03 | Developer 2[10%] | 0% |
| 86 | Module 3: Analysis of Variance content complete | 0 days | Tue 29/07/03 | Tue 29/07/03 | | 0% |
| 87 | Module 4: Non-Parametric Statistics | 2 days | Thu 31/07/03 | Fri 01/08/03 | | 0% |
| 88 | Gather content | 1 day | Fri 01/08/03 | Fri 01/08/03 | Instructional Designer[10%],Instructor[25%] | 0% |
| 89 | Develop content | 2 days | Thu 31/07/03 | Fri 01/08/03 | Developer 2[10%] | 0% |
| 90 | Module 4: Non-Parametric Statistics content complete | 0 days | Fri 01/08/03 | Fri 01/08/03 | | 0% |
| 91 | Module 5: Lying with Statistics | 3 days | Mon 04/08/03 | Wed 06/08/03 | | 0% |
| 92 | Gather content | 1 day | Mon 04/08/03 | Mon 04/08/03 | Instructional Designer[10%],Instructor[25%] | 0% |
| 93 | Develop content | 2 days | Tue 05/08/03 | Wed 06/08/03 | Developer 2[10%] | 0% |
| 94 | Module 5: Lying with Statistics content complete | 0 days | Wed 06/08/03 | Wed 06/08/03 | | 0% |
| 95 | Create FAQ (help section) | 4 days | Thu 07/08/03 | Tue 12/08/03 | | 0% |
| 96 | Decide on font style, length, look and feel | 2 hrs | Thu 07/08/03 | Thu 07/08/03 | Instructional Designer[10%],Instructor[10%],Developer 2[10%],Graphics Support[3%] | 0% |
| 97 | Develop FAQ | 3 days | Fri 08/08/03 | Tue 12/08/03 | Developer 2[10%] | 0% |
| 98 | Obtain approval to proceed | 2 hrs | Tue 12/08/03 | Tue 12/08/03 | Project Manager[10%],Management[10%] | 0% |
| 99 | FAQ complete | 0 days | Tue 12/08/03 | Tue 12/08/03 | | 0% |
| 100 | Database Development | 15 days | Thu 07/08/03 | Wed 27/08/03 | | 0% |
| 101 | Develop questions | 3 days | Thu 07/08/03 | Mon 11/08/03 | Instructional Designer[10%],Instructor[25%] | 0% |
| 102 | Develop database program | 5 days | Fri 15/08/03 | Thu 21/08/03 | Developer 1[75%] | 0% |
| 103 | Test database program | 2 days | Fri 22/08/03 | Mon 25/08/03 | Developer 1[75%] | 0% |
| 104 | Enter questions into database | 2 days | Tue 26/08/03 | Wed 27/08/03 | Instructional Designer[5%],Developer 2[10%],Graphics Support[10%],Support Staff[50%] | 0% |
| 105 | Database development complete | 0 days | Wed 27/08/03 | Wed 27/08/03 | | 0% |
| 106 | Assembly | 4 days | Mon 25/08/03 | Thu 28/08/03 | | 0% |
| 107 | Convert to delivery format, handle paging, tracking | 4 days | Mon 25/08/03 | Thu 28/08/03 | Developer 2[50%] | 0% |
| 108 | Assembly complete | 0 days | Thu 28/08/03 | Thu 28/08/03 | | 0% |
| 109 | Web Site Evaluation | 4 days | Tue 26/08/03 | Fri 29/08/03 | | 0% |
| 110 | Testing and Revising Web Site | 4 days | Tue 26/08/03 | Fri 29/08/03 | | 0% |
| 111 | Alpha Testing | 1 day | Tue 26/08/03 | Tue 26/08/03 | Developer 1[10%],Developer 2[10%],Instructional Designer[10%],Instructor[10%],Project Manager[10%] | 0% |
| 112 | Beta Testing | 1 day | Wed 27/08/03 | Wed 27/08/03 | Developer 1[10%],Developer 2[10%],Instructional Designer[10%],Instructor[10%],Project Manager[10%] | 0% |
| 113 | Revise web site | 1 day | Fri 29/08/03 | Fri 29/08/03 | Developer 2[15%],Developer 1[15%] | 0% |
| 114 | Obtain approval to proceed | 2 hrs | Fri 29/08/03 | Fri 29/08/03 | Project Manager[10%],Management[10%],Instructor[10%],Developer 1[10%],Developer 2[10%] | 0% |
| 115 | Testing and Revising complete | 0 days | Fri 29/08/03 | Fri 29/08/03 | | 0% |
| 116 | Project Evaluation | 4 days | Tue 02/09/03 | Fri 05/09/03 | | 0% |
| 117 | Performance evaluation | 4 days | Tue 02/09/03 | Fri 05/09/03 | Project Manager[10%] | 0% |
| 118 | Performance against goals | 4 days | Tue 02/09/03 | Fri 05/09/03 | Project Manager[10%] | 0% |
| 119 | Performance against schedule | 4 days | Tue 02/09/03 | Fri 05/09/03 | Project Manager[10%] | 0% |
| 120 | Performance against quality | 4 days | Tue 02/09/03 | Fri 05/09/03 | Project Manager[10%] | 0% |
| 121 | Performance against budget | 4 days | Tue 02/09/03 | Fri 05/09/03 | | 0% |
| 122 | Performance evaluation complete | 0 days | Fri 05/09/03 | Fri 05/09/03 | | 0% |
| 123 | Project Planning Evaluation | 2 days | Mon 08/09/03 | Tue 09/09/03 | | 0% |
| 124 | Identify limitations (well defined plan, meetings, communication, changes, etc…) | 2 days | Mon 08/09/03 | Tue 09/09/03 | Project Manager[5%],Instructional Designer[5%],Developer 1[5%],Developer 2[5%],Graphics Support[5%],Support Staff[5%] | 0% |
| 125 | Make recommendations | 2 days | Mon 08/09/03 | Tue 09/09/03 | Project Manager[10%] | 0% |
| 126 | Project evaluation complete | 0 days | Tue 09/09/03 | Tue 09/09/03 | | 0% |